Phnom Penh: The cabinet
meeting held on 10 May 2013 approved L.Y.P Group.Co., Ltd to invest in the
development of power transmission lines under the build-operate-transfer
(B.O.T) for 29 years contract with the amount of 92.21 million USD investment
on 230 kilovolt power transmission lines Kampong Cham-Kratie, connecting from
Phnom Penh to eastern province including Kompong Cham, Kratie, Steung Treng,
Ratanakiri and Mondulkiri province.
In order to
develop national transmission lines in compliance with the plan, the government
is preparing to build sub-stations and high-tension transmission lines in three
different destinations. Firstly, connect from Phnom Penh to Kompong Cham so as
to build an electricity supply system base at the eastern province including
Kompong Cham, Kratie and Steung Treng. Secondly, connect from Kompot province
to Preah Sihanouk, sourcing electricity from a coal-fired power plant in Preah
Sihanouk province. Finally, connect from Phnom Penh to Preah Sihanouk province
through national road No 4 to be the Phnom Penh-Kandal-Takeo-Kompot-Preah
Sihanouk circuit system will be built. (Rasmei Kampuchea, 11 May)